| Public Procurement Review
UK High Court rules that public procurement procedure not
subject to judicial review
The UK High Court has dismissed a challenge by an
unsuccessful bidder who had alleged that a public procurement
procedure conducted by the Welsh Assembly and the Forestry
Commissioners was irrational and unfair. The Court held that
there were insufficient public law aspects for it to be
subject to judicial review. In September 2005, the
Forestry Commissioners in Wales tendered for wind farm
development contracts. The tender procedure was
conducted outside the EU procurement rules. Expressions
of interest were invited and interested operators asked to
complete a pre-qualification questionnaire. Bids were
assessed by reference to certain criteria, with each section
scored out of 10 and a score of 5 being sufficient for
pre-qualification. Gamesa Energy UK Limited (Gamesa) was
notified that it had not prequalified. Gamesa claimed
that the decision was flawed, irrational and unfair, and/or
was taken in breach of its legitimate expectation. In
particular, Gamesa claimed that it was not made clear (i) what
information was required in relation to previous project
specific experience; (ii) that no marks would be given for any
uncompleted previous projects. Gamesa also claimed that
the marking system was unfair in the circumstances as marks of
all the projects were taken into consideration, including nil
marks for incomplete projects, and that marks awarded in
relation to past project experience were inconsistent with
marks under other subsections and/or were inherently
irrational. The main question considered by the UK High
Court was whether the procurement process was subject to
judicial review, i.e. whether there was a "sufficient public
law element". The Court held that the fact that the
procurement process was conducted by a public body, in
exercise of statutory functions, and involved the expenditure
of public money, may not be sufficient to justify a judicial
review of the process. The Court went on to say that
there were no sufficient public law aspects in this
case. In particular, the Court noted that, as long as
the process was conducted in good faith and without
corruption, the defendants had a discretion in how it was
carried out. Although the Court did not rule out a
public law challenge to a procurement process on the basis of
irrationality, it stated that the cases where this would be
appropriate would be rare. The Court stated that, to
allow challenges to tendering processes on the basis that the
process is unfair to a particular bidder (but where the
process was conducted in good faith and without
discrimination) would lead to an unreasonable impediment to a
public body. Source: http://competition.practicallaw.com/8-204-0972
|