Careers

Learn more

Qualified professionals

Learn more

Trainee & intern programmes

Learn more

Offices

New York

Learn more

San Francisco

Learn more
A&L Goodbody logo
What is early contractor involvement?

Construction & Engineering

What is early contractor involvement?

Early contractor involvement (ECI) is a procurement and delivery approach under which a contractor is engaged before the main construction works are commenced.

Tue 11 Nov 2025

5 min read

Early contractor involvement (ECI) is a procurement and delivery approach under which a contractor is engaged before the main construction works are commenced. In an ECI approach, the contractor will provide pre‑construction services such as:

Under an ECI approach, a Contractor might also carry out other non-advisory services such as procuring materials with long lead times or carrying out preliminary on-site enabling works.

What is the rationale for using ECI?

The rationale for using ECI on a project is generally some combination of the following:

How is it documented?

There are at least two alternative approaches:

  1. The one contract approach: the parties enter a building contract that has two separate stages: stage one being the preconstruction services and stage two being the physical construction works. The contract will contain specific provisions that allow the employer to control whether or not the stage two works are commenced and when they are commenced.  
  2. The two contract approach: The parties enter into two separate contracts: a pre‑construction services agreement (PCSA) and then subsequently a separate building contract if both parties are happy to proceed.  A near‑final form of the building contract will be appended to the PCSA, with certain commercial terms (particularly around design and pricing) left open for negotiation pending the outcome of the services to be performed under the PCSA.

At present, neither the PWC nor the RIAI forms (including the recently published RIAI forms) contain an ECI mechanic. ECI mechanics have been built into some PWC contracts in the past, but this can only be done on projects over a certain value and with the express permission of the Government Contracts Committee for Construction (GCCC). The GCCC is currently reviewing the issue of ECI and we await to see if the outcome of that review will be the publication of a revised form of PWC contract that includes an ECI mechanic. It is perhaps surprising that the RIAI form has not allowed ECI as an option at least.

In the UK, the NEC form of contract provides for a one contract approach to ECI while the JCT form of contract provides for a two-contract approach.

Points to consider before engaging in ECI

The transition from ECI to construction works

If the contractor is awarded the construction works

If the contractor is awarded the construction works, then issues regarding the contractor’s liability for its preconstruction services and its intellectual property rights over its design will typically be determined by the terms of the building contract entered into. This is regardless of the terms of any contract that has previously been entered into by the parties. The transition between the preconstruction services and the construction works should be clear cut, with the parties clear as to the design, the programme and the budget that is being worked to under the building contract. A failure to ensure this clarity before commencing the construction works can result in disputed variations during the construction phase.

If the contractor is not awarded the construction works

If the contractor is not awarded the construction works, then the liability between the parties will typically be dictated by the terms of the ECI contract (be that a PCSA or a two-stage building contract). It’s therefore important to consider when negotiating these contracts how the relationship will be governed if the contractor is not awarded the construction works.

Issues to consider when the contractor is not awarded the construction works include:

For further information in relation to this topic or any related matter, please contact Conor Owens, Partner, Michael Kennedy, Senior Associate, Paul McNamee, Associate or your usual contact on the Construction & Engineering team.

Date published: 11 November 2025

Key Contacts